- Working on getting the tests to pass upon merging the latest RSPM/VEState commits with the VEGUI/VEScenarioViewer commits
- Current issue appears to be non-replicability in the VEHouseholdVehicle module revisions for RSPM that is causing the tests to produce a different answer each time
- Plan to override VEHouseholdVehicle outputs with one set of outputs for the test system for now and create an issue for @Brian to resolve
- Once tests pass, will merge from develop to master to release the software
- @Matt to update tutorial as a result
- GUI updates completes and works for both RPAT and RSPM, see PR198
- Multi-run analysis and Scenario viewer now working for RSPM in addition to RPAT, see PR223
- Making a few final revisions to clean-up the workflow
- Plan to merge after issue above fixed
- Once merged to master, @Jeremy will build an installer for @Tara to test
- @Jeremy, @Tara and others will then review and provide feedback in January
- Near of Jan, @RSG/BG will officially finish development and VisionEval.org will merge the contributions into the master repo
- Contract ends May 1st
- After completing the current scope above, @RSG/BG will provide pooled funds coordination support under a new task order, with the following tasks
- a technical presentation/workshop with the pooled funds consultant and technical pooled funds members for knowledge transfer
- informal support as needed up to the total hours
- The time period for this support task will be ~2/1-5/1 and it will be around 64 hours of time
- @RSG to do a cost to complete of the existing scope to identify any remaining funds
- @Jacobs to draft contract amendment for RSG support
- Getting Started
- VisionEval Models
- VERPAT Tutorial
- VERSPM Tutorial
- VE-RSPM Training
- Developer Orientation
- Goals and Objectives
- Working Together
- Automated Testing
- Contribution Review Criteria
- Modules and Packages
- Development Roadmap
- Documentation Plan
- Multiple Scenarios