PMBOK p.482
- qq Scope management plan
- qq Requirements management plan
- qq Risk Management plan
- qq Procurement management plan
- Configuration management plan
- qq Cost baseline
Project documents:
- dd Lessons learned register
- dd Project schedule
- dd Requirements documentation
- dd Risk register
- dd Stakeholder register
Procurement documentation Seller proposals
EEF Enterprise Environmental Factors OPA Organizational process assets
Expert judgement - see dd Stakeholder register Advertising Bidder conferences Data analysis Interpersonal and team skills
- Negotiation
new Selected sellers new Agreements -- see Agreement list new dd Change requests
Project management plan updates: root Project management plan
- updates to qq Requirements management plan
- updates to qq Quality management plan
- updates to qq Communications management plan
- updates to qq Risk Management plan
- updates to qq Procurement management plan
- updates to qq Scope baseline
- updates to qq Schedule baseline
- updates to qq Cost baseline
Project document updates:
- updates to dd Lessons learned register
- updates to dd Requirements documentation
- updates to dd Requirements traceability matrix
- updates to dd Resource calendars
- updates to dd Risk register
- updates to dd Stakeholder register
updates to OPA Organizational process assets