PMBOK p.222
Project documents:
- dd Lessons learned register
- dd Project calendars
- dd Project schedule
- dd Resource calendars
- dd Schedule data
Work performance data OPA Organizational process assets
Data analysis:
- Earned value analysis
- Iteration burndown chart
- Performance reviews
- Trend analysis
- Variance analysis
- What-if scenario analysis
Critical path method Project management information system Resource optimization Leads and lags Schedule compression
new Work perfomance information new dd Schedule forecasts new dd Change requests
Project management plan updates: root Project management plan
- updates to qq Schedule management plan
- updates to qq Schedule baseline
- updates to qq Cost baseline
- updates to Performance measurement baseline
Project document updates:
- updates to dd Assumption log
- updates to dd Basis of estimates
- updates to dd Lessons learned register
- updates to dd Project schedule
- updates to dd Resource calendars
- updates to dd Risk register
- updates to dd Schedule data