You signed in with another tab or window. Reload to refresh your session.You signed out in another tab or window. Reload to refresh your session.You switched accounts on another tab or window. Reload to refresh your session.Dismiss alert
We need to create a capital cost page specifically for the MILCON ERCIP project analysis type. It will be a unique page because it will include a line item breakdown of the investment costs, each of which must be reported as its own cost object.
Here are the headings. Each has an input (in $) with 2 decimals:
Construction Cost
SIOH
Design Cost
Total Cost (not editable; its the sum of construction cost, SIOH, and Design Cost)
Salvage Value of Existing Equipment
Public Utility Company Rebate
Total Investment (not editable; its the total cost minus salvage value and rebate)
Instead of generating a single E3 object for this cost page, we need to create 5 cost objects, one for each (non-sum) line item. Those need to be provided in the results. See issue related to displaying ERCIP results.
The text was updated successfully, but these errors were encountered:
We need to create a capital cost page specifically for the MILCON ERCIP project analysis type. It will be a unique page because it will include a line item breakdown of the investment costs, each of which must be reported as its own cost object.
Here are the headings. Each has an input (in $) with 2 decimals:
Construction Cost
SIOH
Design Cost
Total Cost (not editable; its the sum of construction cost, SIOH, and Design Cost)
Salvage Value of Existing Equipment
Public Utility Company Rebate
Total Investment (not editable; its the total cost minus salvage value and rebate)
Instead of generating a single E3 object for this cost page, we need to create 5 cost objects, one for each (non-sum) line item. Those need to be provided in the results. See issue related to displaying ERCIP results.
The text was updated successfully, but these errors were encountered: