With a fairly modest change (to allow rerunning mk5cn in initialization mode), it should be possible to trigger changing to a different recorder while the FS is running. Of course this should not be done while the current recorder is recording. This mechanism can be used by the script you mention. Would it be useful to have this triggered automatically by the schedule? If so, we could consider ways of doing that. |
Beta Was this translation helpful? Give feedback.
-
If FS provides a new feature to re-initialize mk5cn without restarting FS, it would be great. This may be also served as an extension of mk5relink. If we need to change the recorder, I will put the script in the procedure sched_initi, which has been re-defined to initilize some local equipments in the experiement prc file at Onsala. So, this change will be automatically done. |
Beta Was this translation helpful? Give feedback.
-
In #153, @vlbi-jun-yang wrote:
Beta Was this translation helpful? Give feedback.