ERTMS/ETCS Case study in Spin — supplementary material of:

Paolo Arcaini and Jan Kofroň: Validation of the Hybrid ERTMS/ETCS Level 3 using Spin

This page contains the material to our case study of the ERTMS/ETCS Level 3 specification in Promela in Promela. We refer to version 1A dated 14/07/2017. We aimed at modelling and verification of the scenarios contained in the specification as well as at the general verification of safety properties of the system. The following files contain the model of the system:

To run a DSL use case, the spin command line has to define the "dsl" symbol. We advise to use the "-X -B" argument as well:

spin -X -B -Ddsl model.pml

To run a particular scenario from the requirement specification document, the "sce" symbol has to be defined, e.g. for scenario 1:

spin -X -B -Dsce=1 model.pml

To run a random simulation, define neither "dsl" nor "sce":

spin -X -B model.pml

We have discovered a potential assertion violation corresponding to a situation when a train crashes into another one due to disconnection and a too-long mute timer time-out. The details can be found here. The list of requirements covered by the VSS state machine can be found here.