Roadmap

This is our roadmap of waypoints, to be refined over time.

Target Date: 14.5 weeks leading up to 1.0 blockchain launch on 2016-07-01

MVP Goals

  • Incorporate new Proof-of-Work
  • Implement spec security fixes
  • Secure SNARK parameters
  • External security audit of protocol/crypto
  • External security audit of implementation

Schedule

  • By Friday March 18th: parameter setup dry-run meeting.
  • Friday March 11: feature selection freeze (no additions to planned features after this)
  • Monday April 11: feature implementation deadline (feature implementations landed but may have bugs)
  • Friday May 13: security freeze (nothing but security fixes after this)
  • before Wednesday June 1: public parameters available
  • Monday June 6: signed binaries distributed
  • Friday July 1: reward starts

Not blockers for launch but highly desired:

  • Reproducible builds
  • Bitcoin-QT-based wallet