By how much is it over/under budget?
currently it isn’t over or under the budget as the budget is set to 2200 k$ after 7 months and the AC is 2200 k$.
By how many days is it ahead/behind the schedule?
It is two months behind the schedule as the task with the ID 3 is only 50% done after two months where it should be 100%.
By the end of the project, by how much will it be over/under budget?
It will be over budget by 500k$
Cost Variance (CV) = EV – AC = 3700 – 4200 = -500k $
Calculate:
Task 1 completion = 100%
Task 2 completion = 100%
Task 3 completion = 50%
Percentage of completion = (100 + 100 + 50) / 3 = 83.33%
PV = 2200k $
EV = PV * % OF COMPLETION = 2200 * 83.33% = 1833.26k $
AC = 2200k $
BAC = 3700k $
Cost Variance (CV) = EV – AC = 1833.26 – 2200 = -366.74k $
Schedule Variance (SV) = EV - PV = 1833.26 – 2200 = -366.74k $
Cost Performance Index (CPI) = EV / AC = 1833.26 / 2200 = 0.8333
Schedule Performance Index (SPI) = EV / PV = 1833.26 / 2200 = 0.8333
Estimate At Completion (EAC) = BAC / CPI = 4440k $