- Sprint Name: Da Jia "Everyone"
- Scrum Master: OM
- Dashboards
- Product Backlog
- Scrum Wall [developers view]
- Deployed environments
- master [developers only]
- aws cluster (us-east-1)
- staging_aws [testers only]
- production_aws (changelogs)
- z43 cluster (ch-zh)
- staging_z43 [testers only]
- production_z43 (changelogs)
Issue | Title | Presenter | Status | Duration | Start Time |
---|---|---|---|---|---|
#273 | All@Z43 Use o2S: Mother Case | All | In progress | 10 min | 11:05 |
#266 | HW/SW Dev Support Case: Online Material Database for Solid Materials | IP | Paused | 2 min | 11:15 |
#68 | Everybody at z43 uses osparc. S4L Notebooks (Mother Case) | All | In progress | - | 11:17 |
#265 | Search & Discover | PC | In progress | 10 min | 11:17 |
#22 | Fine Grained Access Rights S-D6, Y3M6 | OM SAN | Done | 10 min | 11:27 |
#91 | TI Treatment Planning (demo in "Results" case) | MaG | In Progress | - | 11:37 |
#505 #12 |
Large Models/Results Rendering & Interaction (M9; D4.a). Video streaming Postpro workbench; S-D15, Y3M6 |
IP MaG | In Progress | 10 min | 10:37 |
#13 | Batch application, high throughput computing; S-D14, Y3M11 | OM | Started | 2 min | 11:47 |
#22 | NEUROFAUNA rat, S-D18, Y3M3 | OM | Done | 5 min | 11:49 |
#232 | Team Black [TB-Project Backlog] | OM | In progress | 5 min | 11:54 |
#21 | Onboarding of SPARC computational models S-D1 Y3M1-12 | KZ | In progress | 3 min | 11:59 |
Z43 uses oSparc Documentation | KZ | In progress | 3 min | 12:02 | |
Platform stability | SAN PC | In progress | 5 min | 12:05 |
Deliverable | Due | Title | % Done | Notes |
---|---|---|---|---|
J-D3 | M1 | Retreat prep | 100 | Retreat has taken place |
J-D15 | M1 | Documentation agreement | 75 | Requirements established |
S-D26 | M1 | Idea Lab subaward | 100 | The subaward has been setup and preparations are ongoing |
S-D2 | M2 | OpenCOR / CellML module & PMR S-D2, M2 #1069 | 100 | Two approaches to run OpenCOR models or create OpenCOR-based services have been implemented |
J-D33 | M2 | Publication linking, J-D33, Y3M2,8 #33 | 100 | Meta-data sections throughout SIM-CORE support linking to pdf, webpages; awaiting MAP-CORE functionality to automatically surface publications (based on DOI?) |
J-D3 | M2 | Retreat | 100 | |
J-D6.a | M2 | Conference list | 100 | |
J-D21 | M2 | DRC feedback/issue collection and tracking (Infrastructure) - J-D21 #1065 | 100 | |
J-D28.a | M2 | Portal testing (Testing and Infrastructure) - J-D28 #1066 | 100 | oSPARC end-to-end testing infrastructure established |
J-D7.a | M2 | simple creation of data-processing modules, S-D7, Y3M2,4,5,2-12 #21 | 100 | survey drafted, work on functionality started |
S-D24 | M2 | UI/UX subaward | 100 | first phase contracted, ongoing |
S-D7a | data analysis and visualization | 50 | survey has been drafted | |
S-D3g | metrics | 75 | metrics have been selected and prepared for presentation to steering committee | |
S-D18 | M3 | NEUROFAUNA rat | 75 | |
J-D3e | M3 | DRC Governance strategies | 100 | |
J-D4 | M3 | slide-decks (marketing material) | 100 | Worked on it this sprint- should be completed soon |
J-D16 | ongoing | Workshops and webinars | 50 | one workshop completed, ongoing |
J-D20 | M3 | White paper outlining SPARC data standards and QC metrics for SPARC data depositors | 50 | |
J-D29 | M3 | Data access/cost structure | ||
S-D10 | M4 | macro/templates, towards guided mode | 100 | |
S-D22 | M5 | AWS | 100 | |
S-D12 | M5 | o2S2PARC API | 70 | |
S-D7 b, c | M5 | simple creation of osparc services | 70 | |
S-D20 | M5 | NEUROCOUPLE Keast team collaboration | 20 | |
S-D6 | M6 | Fine-grained access rights | 50 | UI Improvements |
S-D15 | M6 | Advanced Postpro | 70 | |
S-D5 | M7 | IT’IS tissue property database | 100 | |
S-D17 | M7 | Neuro Postpro | ||
S-D4 | M8 | Flatmap Widget | ||
J-D31 | M8 | Notification Service part 1 | ||
S-D3 | M9 | Grill Approach | ||
S-D4 | M9 | Notification service parts 2&4 | ||
S-D8 | M9 | UI for Service Submission | 50 | |
S-D19 | M9 | Neurocouple service | ||
S-D21 | M1-12 | DevOps/Platform stability | ||
- S-D18: decaying rat prevents reimaging required to properly segment the PNS; registration-based approach will be tried, to merge PNS images from previously scanned rat
- Continuous work on Platform stability is time-consuming but essential work and may delay other milestones
- S-D20: Martin Bertrand’s work on the detailed pelvic PNS functionalization will be delayed
- Migration to AWS: High priority tasks related to Z43's energy infrastructure retain our DevOps resources and delay the completion of this one.