Question/Comment on the 14(c) Web Application Tool

Name and affiliation

Izabela Stani, Contracts Administrator, TechFlow, Inc.

Section of RFQ documents

Section 5.1 Milestones of RFQ

Question/Comment

There seems to be a minor discrepancy between the acquisition timeline referenced in RFQ Section 5.1 “Milestones” and what is currently showing in the GSA eBuy portal. Specifically, GSA eBuy references the closing date as “June 26, 2017 12;00PM EDT yet RFQ Section 5.1 indicates that questions are due no later than June 28, 2017 by 3:00PM EST with the Written Quote due no later than July 10, 2017, 2017 by 1:00PM EST.
Please clarify which acquisition timeline is correct, eBuy or RFQ Section 5.1.

@oghaffari
Copy link
Contributor

The dates in eBuy now match the ones in the RFQ on GitHub: Questions must be received by June 28 and submissions by July 10.